OpenProject resource planning and comparing tools
Listen to this lesson
Nigerian voice narration
Fictional training case. The schools connectivity schedule looks good, but you have only four installation engineers, and the Gantt chart shows six schools scheduled in the same week. The Director also asks why the agency should not just use ClickUp, which the IT unit already likes. This lesson covers resource planning in OpenProject and helps you compare the three tools objectively.

Introduction and objectives
A schedule is only realistic if the people to do the work are available. In this lesson you will use OpenProject's team planner and workload views for resource planning, manage task dependencies under resource limits and compare OpenProject, ClickUp and Trello. By the end you should be able to balance resources and justify a tool choice.
Introduction to resource planning
Resource planning matches the work with available people, equipment and money. Each engineer can install one school in about three days, so four engineers handle about six schools per fortnight. If six schools are scheduled in one week, the plan is unrealistic. Resource planning reveals this before engineers are overloaded and quality drops.
Using the team planner
In OpenProject, open 'Team planner', add the four engineers and view by week. Each engineer's assigned work packages appear on their row. Drag work packages between engineers or across weeks to balance the load. Set estimated hours on work packages and check that no one exceeds about 40 hours a week. Reschedule non-critical schools first.
Dependencies under resource limits
Sometimes a task could start but no resource is free. Levelling resources may push tasks later and lengthen the schedule. Protect critical path work first, borrow resources if possible (perhaps an engineer from the agency's maintenance unit), and communicate any new end date through change control rather than quietly overloading staff.

Build the prompt from three phrases — Role, Task and Format — and watch the AI answer.
Comparing OpenProject with other tools
OpenProject: strong Gantt, dependencies, baselines and self-hosting — ideal for structured, audited public-sector projects. ClickUp: flexible, rich features and dashboards — ideal for companies running many mixed projects. Trello: simplest Kanban — ideal for small teams and events. The best choice depends on project complexity, team skills, data hosting needs and budget.
Common mistakes to avoid
The biggest mistake is building a schedule without checking people's availability, then blaming engineers for missing impossible dates. Others include ignoring annual leave and public holidays, overloading the best performer, and choosing a tool because one person likes it without considering the team's needs.
Practice exercise
Using your OpenProject project, assign twelve tasks to three people with estimated hours. Open the team planner and identify any overloaded week. Move tasks to balance workload. Then write a short comparison table of OpenProject, ClickUp and Trello for your own organisation and recommend one.
Lesson summary
Resource planning ensures the schedule fits the people available. OpenProject's team planner shows workload and lets you rebalance tasks. Protect critical work when levelling resources. Choose between OpenProject, ClickUp and Trello based on complexity, team skills, hosting needs and budget.
You are a resource planning adviser. Suggest how to rebalance a schedule where 6 school installations fall in one week but only 4 engineers are available as 5 numbered actions.
Answer all three questions and check your answers to unlock the next lesson. Pass mark: 2 of 3.
Which tool is strongest for self-hosted, audited projects with formal Gantt baselines?
When levelling resources lengthens the project, you should…
Four engineers each installing one school every three days can complete roughly how many schools in a 12-working-day period?
