Scenario two: managing an office relocation
Listen to this lesson
Nigerian voice narration
Fictional training case. Naz-Tech Developers is moving from 88/16 Buzu Street to a larger office across Jos. Management has appointed you Project Manager with a ₦6.5 million budget and five weeks before the old lease ends. Twenty-two staff, servers, client files and the internet connection must move with no more than one day of downtime. You will use ClickUp, Excel and ChatGPT.

Introduction and objectives
An office relocation is a classic Waterfall project with a hard deadline. In this lesson you will develop the relocation plan, identify requirements, prepare a budget, manage suppliers, assign tasks, create a schedule, handle risks and unexpected costs, track progress, coordinate communication and write a completion report.
Plan and requirements
Start with requirements: new office ready (painting, partitions, electrical), internet installed and tested before moving day, 22 workstations, server room with air conditioning, secure transport of client files and a staff seating plan. Use ChatGPT to draft a relocation checklist, then confirm each item with the IT lead, admin officer and landlord.
Budget and suppliers
Excel budget: partitions and painting ₦1.8m; electrical and network cabling ₦1.2m; air conditioners ₦900,000; movers and trucks ₦450,000; new furniture ₦1.1m; internet installation ₦250,000; signage ₦200,000; contingency ₦600,000 — total ₦6.5 million. Get three quotes for each major item, sign written agreements with dates and penalties, and pay deposits only against agreed milestones.
Tasks and schedule
In ClickUp, create the folder 'Office Relocation' with lists: Preparation, Fit-out, IT, Moving Day and Settling In. Assign owners: Admin Officer (movers, furniture), IT Lead (internet, server), you (contractor, landlord). Schedule: week 1 quotes and contracts; weeks 2–3 fit-out; week 4 internet live and test; Friday of week 5 pack; Saturday move; Monday staff resume.

Build the prompt from three phrases — Role, Task and Format — and watch the AI answer.
Risks, communication and completion
Key risks: internet provider delay (order in week 1; backup 4G routers), fit-out overrun (penalty clause), damaged equipment (insured movers, labelled boxes). Communicate weekly to staff by email and notify clients of the new address. After the move, track snags in ClickUp, then write a completion report with budget versus actual, downtime achieved and lessons learned.
Common mistakes to avoid
Common mistakes include ordering internet too late, moving before the new office is finished, poor labelling so equipment ends up in the wrong rooms, forgetting to update the address with banks, CAC, clients and Google Maps, and leaving the old office without a handover inspection, losing the caution deposit.
Practice exercise
Download the relocation task list. Adjust it for your organisation, assign owners and dates over five weeks and import it into ClickUp. Build the Excel budget within ₦6.5 million and write five risks with responses. Finally, draft a staff announcement email with ChatGPT and edit it.
Lesson summary
Manage a relocation with clear requirements, a contingency-backed budget, competitive written supplier agreements, a phased ClickUp schedule, early ordering of long-lead items like internet, active risk responses, regular communication and a completion report.
You are an office relocation project manager. Create a five-week relocation schedule for a 22-person IT company with a ₦6.5 million budget as a week-by-week table with key tasks and owners.
Answer all three questions and check your answers to unlock the next lesson. Pass mark: 2 of 3.
Paying supplier deposits only against agreed milestones helps to…
Backup 4G routers for moving day are an example of…
After the move, which update is often forgotten?
