Project budgeting and resource management
Listen to this lesson
Nigerian voice narration
Fictional training case. Jos North Local Government is running a five-day free medical outreach for 2,000 residents with a budget of ₦7.5 million. You must plan doctors, nurses, drugs, tents, generators, transport and publicity. Last year a similar outreach ran out of drugs on day three and paid ₦600,000 extra for emergency purchases. This lesson teaches you to estimate costs, allocate resources and control spending.

Introduction and objectives
A realistic budget and the right resources at the right time are central to project success. In this lesson you will learn to estimate costs, identify human and material resources, allocate them, monitor expenditure and manage budget changes. By the end you should be able to build and control a project budget.
Estimating project costs
Use bottom-up estimating: cost each work package, then add up. Drugs: 2,000 patients × ₦1,800 average = ₦3.6 million. Medical staff: 10 doctors × 5 days × ₦40,000 = ₦2 million. Tents and chairs ₦450,000, generator and fuel ₦350,000, transport ₦300,000, publicity ₦200,000. Add a contingency reserve of 5–10% for known risks; here ₦400,000.
Human and material resources
Human resources are the people and skills needed: doctors, nurses, pharmacists, registration clerks, security and volunteers. Material resources are equipment and supplies: drugs, test kits, tents, generators, vehicles. List quantities and dates for each, because a doctor booked for the wrong week is as useless as no doctor.
Allocating resources
Allocate resources to tasks and days, and watch for over-allocation, such as one pharmacist scheduled at two sites at once. A simple resource table shows each resource, task, days and cost. If 600 patients are expected on day one, schedule more registration clerks that morning rather than spreading them evenly.

Build the prompt from three phrases — Role, Task and Format — and watch the AI answer.
Monitoring expenditure and budget changes
Track actual spending against budget daily or weekly: Budget, Committed (orders placed), Actual (paid) and Variance. If drugs are being used faster than planned, act on day two, not day four. Budget changes should be requested formally, justified, approved by the sponsor and recorded so the final report explains every difference.
Common mistakes to avoid
Common errors include guessing a single total instead of costing each item, forgetting transport, fuel and bank charges, and spending the contingency on nice-to-haves. Another is tracking only payments and ignoring commitments, which hides how much money is truly left. Never move money between budget lines without approval.
Practice exercise
Build a bottom-up budget for a small project with at least eight cost lines, showing quantity, unit cost and total in Naira. Add a 7% contingency. Then list five human and five material resources with the days each is needed.
Lesson summary
Estimate costs bottom-up and add a contingency reserve. Identify and allocate human and material resources to specific tasks and dates. Monitor budget, commitments, actuals and variances regularly, and approve budget changes formally.
You are a project finance officer for public health programmes. Prepare a bottom-up budget for a five-day medical outreach for 2,000 people within ₦7.5 million as a table: item, quantity, unit cost, total, plus contingency.
Answer all three questions and check your answers to unlock the next lesson. Pass mark: 2 of 3.
Money set aside for known but uncertain risks is called…
Scheduling one pharmacist at two outreach sites on the same day is…
Why track committed costs as well as actual payments?