Scheduling: durations, dependencies, Gantt charts and the critical path

Listen

Nigerian voice narration

Scenario

Fictional training case. Unity Bank's Jos branch is being refurbished, and it must reopen in 30 days because customers are already complaining. Tasks include removing old fittings, electrical rewiring, POP ceiling, painting, installing counters and setting up the ATM. The contractor says everything can happen at once. You know some tasks must wait for others. This lesson teaches you to build a realistic schedule and find the tasks that cannot slip.

A planner organising tasks, timelines and a budget

Introduction and objectives

A schedule turns the WBS into a timeline. In this lesson you will learn to estimate durations, identify task dependencies, draw a Gantt chart, find the critical path and handle delays. By the end you should be able to produce a schedule that shows which tasks control the finish date.

Estimating duration

Estimate how long each task takes using past experience, expert advice or a three-point estimate: (Optimistic + 4 × Most likely + Pessimistic) ÷ 6. If rewiring could take 4, 6 or 11 days, the estimate is (4 + 24 + 11) ÷ 6 = 6.5 days. Include realistic factors like public holidays, power outages and supplier delivery times.

Task dependencies

Dependencies show the order tasks must follow. The most common is finish-to-start: painting cannot start until the POP ceiling finishes. Others include start-to-start (two tasks begin together) and finish-to-finish. For the branch: remove fittings → rewiring → POP ceiling → painting → install counters. ATM setup depends only on rewiring and can run in parallel with painting.

Gantt charts

A Gantt chart shows tasks as horizontal bars against a calendar. Bar length is duration, arrows show dependencies and diamonds mark milestones. Managers can see at a glance what should be happening today and what is late. You can draw one in Excel with a stacked bar chart, or let ClickUp or OpenProject draw it automatically.

Colleagues checking an AI response against source documents
Prompt practice

Build the prompt from three phrases — Role, Task and Format — and watch the AI answer.

The critical path and managing delays

The critical path is the longest chain of dependent tasks; it sets the earliest finish date. Here: fittings (3) + rewiring (7) + ceiling (6) + painting (5) + counters (4) = 25 days. Tasks on it have zero float, so any delay delays the opening. ATM setup (5 days) has float. When delays occur, add resources to critical tasks or overlap them carefully, and update the schedule immediately.

Common mistakes to avoid

Common mistakes include scheduling every task to start on day one, ignoring dependencies, and using wishful estimates without buffers. Another is focusing on easy non-critical tasks while a critical task slips quietly. Finally, a schedule that is never updated after delays becomes useless within a week.

Practice exercise

List eight tasks for a project of your choice with durations and dependencies. Identify every path from start to finish, add up each, and mark the critical path. Draw a simple Gantt chart on paper or in Excel and note which tasks have float.

Lesson summary

Estimate durations realistically, link tasks with dependencies, and display them on a Gantt chart. The critical path is the longest dependent chain and determines the finish date; protect it closely and update the schedule when delays happen.

Try this prompt

You are a scheduling expert. Find the critical path for a bank branch refurbishment: fittings 3 days, rewiring 7, ceiling 6, painting 5, counters 4, and ATM setup 5 days after rewiring as a table of paths with totals, then the critical path.

Checkpoint · 3 questions

Answer all three questions and check your answers to unlock the next lesson. Pass mark: 2 of 3.

Optimistic 4, most likely 6, pessimistic 11 days gives a three-point estimate of…

'Painting cannot start until the ceiling is finished' is which dependency?

On a Gantt chart, a diamond symbol usually represents…