Scope, deliverables, the WBS and avoiding scope creep
Listen to this lesson
Nigerian voice narration
Fictional training case. Naz-Tech has been asked by a Jos law firm to 'set up their office IT'. The partner says it casually, with a budget of ₦5.5 million. Three weeks in, they also want CCTV, a staff email training session and a new website — at no extra cost. Your team is exhausted and the budget is gone. This lesson shows how a clear scope and a Work Breakdown Structure would have prevented this.

Introduction and objectives
Scope defines exactly what a project will and will not deliver. In this lesson you will learn to write a scope statement, list deliverables and requirements, build a Work Breakdown Structure (WBS), set milestones and control scope creep. By the end you should be able to break any project into manageable, assignable work.
Scope, deliverables and requirements
The scope statement describes the work included and, just as importantly, what is excluded. Deliverables are tangible outputs: 12 configured laptops, a network with Wi-Fi, a shared file server, a backup system and a user guide. Requirements are conditions each deliverable must meet, such as 'Wi-Fi covers all four rooms' or 'nightly automatic backup'. Exclusions: CCTV, website and training.
Building the WBS
A Work Breakdown Structure breaks the project into smaller parts in levels. Level 1 is the project: Law Firm IT Setup. Level 2 lists major deliverables: Hardware, Network, Server and Backup, Documentation. Level 3 breaks each into work packages: Hardware → procure laptops, install software, configure accounts. Stop when a package can be estimated, assigned and finished in a few days.
Milestones
Milestones are significant points with zero duration that mark progress, such as 'Hardware delivered', 'Network live' and 'Client sign-off'. They are useful for reporting to the sponsor and often trigger payments: for example, 40% on signing, 40% when the network is live, 20% on sign-off.

Build the prompt from three phrases — Role, Task and Format — and watch the AI answer.
Avoiding scope creep
Scope creep is uncontrolled growth in scope without matching time or money. Prevent it by getting the scope statement signed, listing exclusions, and handling every new request through a change request: describe the change, estimate cost and time, and get written approval. CCTV could be added for ₦1.2 million and one more week — if the partner signs.
Common mistakes to avoid
The biggest mistake is a vague scope like 'set up IT'. Others include saying yes to small extras to keep the client happy until they add up, building a WBS of activities instead of deliverables, and breaking work so finely that tracking becomes impossible. Always write down what is excluded.
Practice exercise
For an event or office project you know, write a scope statement with five deliverables and three exclusions. Build a three-level WBS with at least twelve work packages. Mark three milestones and write one sample change request for an extra item, with its cost and time impact.
Lesson summary
A clear scope statement lists deliverables, requirements and exclusions. The WBS breaks the project into manageable work packages, and milestones mark key progress points. Scope creep is controlled by a signed scope and a formal change request process.
You are an IT project manager. Create a three-level Work Breakdown Structure for setting up office IT for a 12-person law firm as an indented list with level numbers.
Answer all three questions and check your answers to unlock the next lesson. Pass mark: 2 of 3.
Level 2 of a WBS usually lists…
A milestone such as 'Network live' has a duration of…
Why list exclusions in a scope statement?