Managing changes and reporting status to management
Listen to this lesson
Nigerian voice narration
Fictional training case. Midway through the seed distribution project, the Commissioner asks you to add 800 farmers from a newly created cooperative. Separately, the transport contractor wants a 15% price increase because of fuel costs. You also need to send a progress report to the Permanent Secretary by Friday. This lesson shows you how to handle change requests properly and report status clearly.

Introduction and objectives
Changes are normal in projects; uncontrolled changes are dangerous. In this lesson you will learn a change control process, how to assess the impact of a change, and how to prepare a clear progress report and communicate status to management using a RAG rating. By the end you should be able to manage changes and report confidently.
The change control process
Every change follows the same path: 1. Log the request in a change log. 2. Assess its impact on scope, time, cost, quality and risk. 3. Recommend approve, reject or defer. 4. The sponsor or change board decides. 5. Update the plan, budget and schedule. 6. Communicate the decision. No change is implemented before approval, however senior the requester.
Assessing impact
Adding 800 farmers at ₦12,000 per farmer costs ₦9.6 million and adds about two weeks. The transport increase of 15% on a ₦8 million contract is ₦1.2 million. Together, the project needs ₦10.8 million more. Present options: approve with extra funding, approve but extend the deadline, or defer the new farmers to phase two.
Preparing a progress report
A good progress report fits on one or two pages: project name and period; overall status; achievements this period; planned work next period; KPIs against targets; budget spent versus planned; top risks and issues; change requests; and decisions needed from management. Use numbers and short sentences. Attach detailed trackers rather than pasting them in.

Build the prompt from three phrases — Role, Task and Format — and watch the AI answer.
Communicating status with RAG
RAG ratings summarise status at a glance. Green: on track. Amber: problems exist but are being managed. Red: serious problems that need management action. This week: Schedule Amber (SPI 0.76, recovery plan in place), Cost Amber (CPI 0.84), Scope Red (change request awaiting decision). Always pair a red or amber with the action or decision required.
Common mistakes to avoid
The worst mistake is implementing a senior person's verbal change without assessing cost or getting written approval, then being blamed for the overrun. Others include 'watermelon reporting' (green outside, red inside), reports full of activities with no numbers, and asking management for decisions without giving options.
Practice exercise
Write a change request for adding a new requirement to a project you know, with cost, time and risk impact and three options. Then write a one-page progress report with RAG ratings for schedule, cost and scope, and two decisions needed from management.
Lesson summary
Control changes through logging, impact assessment, formal approval and plan updates. Report progress briefly with numbers, risks, changes and decisions needed. Use RAG ratings honestly and always link red or amber status to an action.
You are a project reporting specialist for government programmes. Write a one-page progress report summary for a seed distribution project that is behind schedule with a pending change request with headings: Status (RAG), Achievements, Next Period, Risks, Decisions Needed.
Answer all three questions and check your answers to unlock the next lesson. Pass mark: 2 of 3.
800 extra farmers at ₦12,000 each cost…
'Watermelon reporting' means…
An Amber status should be accompanied by…