Tracking progress and measuring performance
Listen to this lesson
Nigerian voice narration
Fictional training case. The Plateau State Ministry of Agriculture is distributing improved seeds and fertiliser to 5,000 farmers in 12 weeks with ₦60 million. At week six, the Commissioner asks, 'Are we on track?' The field officer says 'we are doing well', but you have no figures to show. This lesson teaches you to measure progress objectively and spot delays before they become crises.

Introduction and objectives
Monitoring compares what is actually happening with what was planned. In this lesson you will learn to track tasks and deadlines, use simple performance measures, calculate schedule and cost performance, and identify delays early. By the end you should be able to answer 'Are we on track?' with evidence.
Tracking tasks and deadlines
Keep a task tracker with each task, owner, planned start and finish, actual dates, percent complete and status (Not started, On track, At risk, Late, Done). Update it weekly from evidence, not opinion: distribution lists signed by farmers, warehouse stock records and payment vouchers. Tools such as ClickUp and Trello make this visible to the whole team.
Key performance indicators
Choose a few KPIs linked to objectives: farmers reached, bags distributed, cost per farmer, percentage of LGAs completed and complaints received. At week six, 1,900 of 5,000 farmers have been reached — 38%, against a planned 50%. That one figure tells the Commissioner more than 'we are doing well'.
Simple earned value
Earned value compares money spent with work done. Planned Value (PV) is the budgeted cost of work scheduled so far: 50% × ₦60m = ₦30m. Earned Value (EV) is the budgeted cost of work actually done: 38% × ₦60m = ₦22.8m. Actual Cost (AC) is what was spent: ₦27m. Schedule Performance Index = EV ÷ PV = 0.76 (behind). Cost Performance Index = EV ÷ AC = 0.84 (over cost).

Build the prompt from three phrases — Role, Task and Format — and watch the AI answer.
Identifying and diagnosing delays
An SPI or CPI below 1 is a warning. Find the cause: late fund release, trucks breaking down, bad roads in two LGAs, or farmer lists not verified. Look at the critical path tasks first. Then propose recovery actions — extra trucks, weekend distribution, or reprioritising accessible LGAs — and show their cost and time effect.
Common mistakes to avoid
Reporting progress by feeling ('almost done') rather than evidence is the most common mistake. Others include measuring activity (meetings held) instead of results (farmers reached), updating trackers only before management visits, and hiding bad news. Remember that 90% complete for weeks usually means a hidden problem.
Practice exercise
For a project with a ₦10 million budget planned to be 60% complete by now, with 45% actually done and ₦7 million spent, calculate PV, EV, SPI and CPI. Write two sentences explaining what the numbers mean and one recovery action.
Lesson summary
Track tasks with evidence-based status updates and a few meaningful KPIs. Earned value compares planned work, completed work and actual cost; SPI and CPI below 1 signal delays or overspending. Diagnose causes quickly and propose recovery actions.
You are a monitoring and evaluation officer. Calculate earned value for a ₦60 million seed distribution project that planned 50% completion, achieved 38% and spent ₦27 million as PV, EV, AC, SPI and CPI with a one-line meaning each.
Answer all three questions and check your answers to unlock the next lesson. Pass mark: 2 of 3.
A CPI of 0.84 means…
Which is a results KPI rather than an activity measure?
1,900 of 5,000 farmers reached is what percentage?