Lesson 5 of 6 · 6 min

AI for progress reports, risk registers, delay analysis and recommendations

Listen

Nigerian voice narration

Scenario

Fictional training case. At week four of the youth ICT project, three things go wrong: a trainer resigns, NEPA outages cancel two sessions and spending on fuel is 40% above plan. The CSR manager wants a progress report with an honest explanation and recommendations by Friday. This lesson shows how AI can help you analyse the situation and draft the report, risk register and recommendations.

A project manager drafting plans with an AI assistant

Introduction and objectives

When projects hit trouble, managers must analyse quickly and report honestly. In this lesson you will use AI to draft progress reports, identify and register risks, analyse causes of delays and generate improvement recommendations. By the end you should be able to turn messy facts into a clear, evidence-based report.

Generating progress reports

Give AI the facts: planned versus actual sessions, attendance, spending by line and issues. Prompt: 'Write a one-page progress report with RAG status for schedule, cost and scope, achievements, issues, and decisions needed. Use only these figures.' Then check RAG ratings are honest; AI tends to soften bad news.

Identifying risks and building a risk register

Prompt: 'Based on these issues, identify eight risks for the remaining two weeks, scoring probability and impact from 1 to 5, with response, owner and trigger, as a table.' AI might add 'second trainer resignation' and 'fuel price increase'. Adjust scores using your local knowledge and assign real owners.

Analysing project delays

Ask AI to apply a root-cause method: 'Using the 5 Whys, analyse why two sessions were cancelled.' Sessions cancelled → no power → generator not fuelled → fuel budget exhausted → fuel was underestimated at 4 hours per day when outages average 7. AI structures the thinking; you confirm each 'why' with facts from the site.

An employee assembling a prompt from three structured blocks
Prompt practice

Build the prompt from three phrases — Role, Task and Format — and watch the AI answer.

Generating recommendations

Prompt: 'Suggest five practical recommendations to recover the schedule within ₦250,000, with cost and expected benefit.' Options may include two Saturday make-up sessions, a hybrid solar-inverter rental, and engaging a replacement trainer from the trainer pool. Choose those that are realistic and add them to the report's 'decisions needed' section.

Common mistakes to avoid

Mistakes include letting AI write a cheerful report that hides problems, accepting generic recommendations like 'improve communication' with no cost or owner, and skipping the evidence behind each root cause. Never feed AI blame-filled notes about named individuals; describe facts neutrally.

Practice exercise

Write five facts about a project that is behind schedule. Use AI to produce a RAG progress report, a 5 Whys analysis for one delay and five costed recommendations. Edit the output, then list which recommendations you would actually choose and why.

Lesson summary

AI helps draft honest progress reports, risk registers, root-cause analyses and recommendations when you give it accurate facts. Check RAG honesty, adjust risk scores with local knowledge, confirm each root cause with evidence and choose only practical, costed recommendations.

Try this prompt

You are a project analyst. Apply the 5 Whys to explain why two training sessions were cancelled at a Jos youth ICT project as 5 numbered whys ending with a root cause and one fix.

Checkpoint · 3 questions

Answer all three questions and check your answers to unlock the next lesson. Pass mark: 2 of 3.

The '5 Whys' technique is used to…

A useful AI-generated recommendation should include…

A fuel budget of ₦200,000 overspent by 40% means actual spending of…